Keep up to dateHow Tarmac aims to prove best practice | |
Performance indicator | Performance target |
Cost reduction | Reducing the winning tender cost from £36m to £32m |
Time reduction | The original tender said 20 months on site, now Tarmac aims to hand over in 17 |
Defects | Aiming for zero defects at handover |
Client changes | Aiming to keep changes low and satisfaction high. Only time will tell |