Keep up to dateCapital costs for a typical 4000 m2 industrial unit | ||
element cost £ | cost/m2 gifa £ | |
Substructure | 206 100 | 51.54 |
Excavate to reduce levels, disposal of excavated material from site | 22 000 | 5.5 |
In situ concrete slab; granular sub base and so on; 35 KN/m2 | 127 900 | 31.98 |
Reinforced concrete ground beams | 17 300 | 4.33 |
Reinforced concrete column portal bases | 25 000 | 6.25 |
Reinforced concrete column portal bases to offices | 4 100 | 1.03 |
Facing brickwork below damp-proof course; 300 mm high | 9 800 | 2.45 |
External walls | 100 000 | 25 |
Blockwork inner skin to external walls of warehouse | 14 900 | 3.73 |
Facing brickwork at low levels | 7 000 | 1.75 |
Vertical sheet cladding, profiled metal cladding | 12 900 | 3.23 |
Vertical sheet cladding; Ward’s Moduclad DW 1000 horizontal | ||
flat panel cladding to suit additional height of building | 48 300 | 12.08 |
Extra over vertical sheet cladding for fire protection | 1 900 | 0.48 |
Curtain walling | 15 000 | 3.75 |
Inner walls | 15 500 | 3.88 |
Block main compartment wall | 9 300 | 2.33 |
Fire lining to head of walls | 1 900 | 0.48 |
Block walls to cores, reception and WCs | 4 300 | 1.08 |
Floors | 11 000 | 2.75 |
Precast concrete floor beams | 11 000 | 2.75 |
Stairs | 6 200 | 1.55 |
Steel cat ladder for roof access | 1 000 | 0.25 |
Precast concrete staircase | 5 200 | 1.3 |
Roof | 162 800 | 40.7 |
Plastisol-coated profiled standing-seam metal-sheet roofing system; | ||
6° pitch; insulation; metal liner trays; 10% GRP profiled rooflights | 133 700 | 33.43 |
Roof penetrations for services | 2 200 | 0.55 |
Mansafe roof access system | 12 900 | 3.23 |
Soffit to eaves | 14 000 | 3.5 |
Frames | 163 800 | 40.95 |
Steel portal frame including purlins and sheeting rails | 112 000 | 28 |
Structural steel framing to offices | 12 100 | 3.03 |
Fire protection and decoration to structural steelwork | 39 700 | 9.93 |
External wall openings | 30 200 | 7.55 |
Polyester powder-coated finished aluminium windows 1200 mm high | 20 700 | 5.18 |
Cill boards and decoration | 700 | 0.18 |
Electrically operated sectional overhead loading doors; | ||
3500 × 4500 mm; decoration; without vision panels | 5 300 | 1.33 |
Double-skinned mild steel fire escape doors | 3 500 | 0.88 |
Internal wall openings | 5 200 | 1.3 |
Solid beech veneered internal single door to cores, WCs and so on | 5 200 | 1.3 |
Balustrading | 12 000 | 3 |
Stainless steel handrail and balustrade | 7 500 | 1.88 |
Painted steel handrail and balustrade | 4 500 | 1.13 |
Internal wall finishes | 11 200 | 2.8 |
Two coats plaster; one mist and two full coats eggshell emulsion | 8 200 | 2.05 |
Render and white glazed wall tiling (full height) | 800 | 0.2 |
Paint to internal face of walls in warehouse and workshop | 2 200 | 0.55 |
Floor finishes | 14 200 | 3.55 |
Cement and sand screed; 75 mm thick | 3 500 | 0.88 |
Carpet tiles; allow PC sum £15/m2 supply | 6 000 | 1.5 |
Ceramic tiling and screed to reception | 1 500 | 0.38 |
Ceramic tiling to WCs including screed and skirting | 800 | 0.2 |
Softwood skirting; decoration | 1 500 | 0.38 |
Ceramic tiled skirting to reception | 300 | 0.08 |
Matwell; frame and mat | 600 | 0.15 |
Stair finishes | 1 000 | 0.25 |
Carpet tiles to treads of flight of stairs; nosings | 1 000 | 0.25 |
Ceiling finishes | 7 900 | 1.98 |
Suspended ceiling; 600 × 600 mm mineral fibre tiles; | ||
exposed T-grid system; fire breaks | 7 700 | 1.93 |
Suspended ceiling; 600 × 600 mm mineral fibre tiles; | ||
exposed T-grid system; to WCs | 200 | 0.05 |
Internal drainage | 21 900 | 5.48 |
Soil and vent to WCs | 1 200 | 0.3 |
Eaves and parapet gutters and fittings; | ||
bituminious paint to inside surfaces | 16 400 | 4.1 |
External aluminium rainwater pipes and fittings; | ||
polyester powder-coated finish | 4 300 | 1.08 |
Water supply | 3 600 | 0.9 |
Cold water installation | 1 700 | 0.43 |
Hot water installation | 800 | 0.2 |
Local hot water heaters | 800 | 0.2 |
Builders’ work | 300 | 0.08 |
Space heating | 21 500 | 5.38 |
Low-pressure hot water radiator heating to first-floor offices | 19 800 | 4.95 |
Builders’ work | 1 700 | 0.43 |
Ventilation | 9 500 | 2.38 |
Mechanical ventilation to WCs | 9 000 | 2.25 |
Builders’ work | 500 | 0.13 |
Power supplies | 46 200 | 11.55 |
Sub-mains distribution to first floor and reception | 5 900 | 1.48 |
Twin switched socket outlets to cores/reception | 600 | 0.15 |
Skirting trunking to offices | 9 800 | 2.45 |
600 × 600 mm recessed lighting to offices/reception | 14 200 | 3.55 |
600 × 600 mm lighting to WCs/cores | 2 100 | 0.53 |
Emergency lighting to warehouse | 1 700 | 0.43 |
Lightning protection | 5 700 | 1.43 |
Power to overhead doors | 1 000 | 0.25 |
Working drawings and manuals | 3 500 | 0.88 |
Builders’ work | 1 700 | 0.43 |
Lifts | 31 500 | 7.88 |
Eight-person passenger lift | 26 000 | 6.5 |
Lift pit base | 4 000 | 1 |
Builders’ work | 1 500 | 0.38 |
Security | 700 | 0.18 |
Fire alarm conduit to offices | 700 | 0.18 |
General fittings | 3 650 | 0.91 |
Duct panel full height to WC | 1 200 | 0.3 |
Vanity top/base unit | 1 250 | 0.31 |
WC partition two-door | 1 200 | 0.3 |
Sanitary fittings | 4 800 | 1.2 |
Lavatory basins | 500 | 0.13 |
WC suites | 600 | 0.15 |
Urinals | 200 | 0.05 |
Mirrors | 1 200 | 0.3 |
Disabled WC/hand basin complete with grab rails and so on | 2 300 | 0.58 |
General siteworks | 238 900 | 59.73 |
Excavate to reduce levels; remove from site | 26 300 | 6.58 |
Service yard and feeder road comprised of concrete; | ||
reinforcement and granular sub-base | 125 000 | 31.25 |
Car parking area comprising macadam paving | 28 000 | 7 |
Pedestrian paving | 11 500 | 2.88 |
Soft landscaping to planting beds | 25 600 | 6.4 |
External watering points and landscaping maintenance | 2 000 | 0.5 |
Steel painted bollards to loading doors | 1 400 | 0.35 |
External lighting | 13 300 | 3.33 |
External floodlight to goods door | 800 | 0.2 |
Crossover works | 5 000 | 1.25 |
Drainage | 96 200 | 24.05 |
Drainage; pipework; surrounds; brick manholes; | ||
trapped gullies; sewer connections | 96 200 | 24.05 |
Installations | 13 400 | 3.35 |
Water supply | 900 | 0.23 |
440 V electrical supply | 2 600 | 0.65 |
100 mm diameter PVCu duct | 3 200 | 0.8 |
Gas supply | 1 500 | 0.38 |
Service trenches | 5,200 | 1.3 |
Preliminaries | 222 000 | 55.5 |
Preliminaries | 200 000 | 50 |
Inflation to start on site | 22 000 | 5.5 |
Total | 1 460 950 | 365.24 |
Maintenance costs for a 4000m2 industrial unit over 25 years  | ||||||
Basic project | Project typical of current market trends | |||||
Specification | Capital cost | Maintenance costs/year | Specification | Capital cost | Maintenance costs/year | Comments |
Roof | ||||||
Profiled steel sheet | 112 000 | 9 000 | Standing seam roof | 133 700 | 7 500 | Maintenance costs for basic project exclude potential disruption to tenants’ operation caused by effect of roof leaks. |
Insulation (0.45 U-value) | 16 000 | 4 200 | Insulation (0.25 U-value) | 32 000 | 3 700 | Improved insulation is particularly attractive to tenants of larger units and those with specific heating requirements. |
External walls | ||||||
Brickwork cavity wall | 44 000 | 120 | Profiled steel sheet composite cladding panel | 13 000 | 1 100 | Damage to brickwork is more difficult to match, which can have longer-term effects on building aesthetics. |
Gutters | ||||||
Valley gutter | 9 500 | 275 | Eaves gutter | 16 500 | 150 | Leaking valley gutters can have long-term corrosion implications on steel frames |
Protection | ||||||
No protection to openings | – | 600 | Steel bollards to door openings, high-profile kerbs to vulnerable areas | 4 400 | 100 | Bollards may need replacing. |
External surfaces | ||||||
60 mm block paviours | 15 000 | 160 | 80 mm block paviours | 17 500 | 0 | Replacement of paviours to damaged areas can cause considerable disruption to tenants’ operations. |
Landscaping | ||||||
Low-quality | 15 000 | 1 700 | High-quality low-maintenance | 26 000 | 1 400 | Low-quality landscaping may need to be replaced more regularly. |