Barnes is confirming what most specialist contractors already know 鈥 that if they get involved in a project鈥檚 design early, they can save cost and time. At Wattisham, 12 weeks have been cut from a 54-week programme 鈥 a saving of 22%. The team is already starting to decamp from site huts, ready for completion this week. As for money, early indications are that the project will also show a 10% reduction in whole-life costs.
The established way of procuring a building is for consultants to produce detailed designs based on their interpretation of what the client wants. These designs are then passed to the specialists, which price them and provide production information. The essence of the new approach being tested at Wattisham, and a similar project at Aldershot, is that specialists contribute to the detailed design, to discussions on buildability and to cost estimates throughout the project.
The specialists鈥 involvement began at the first client meeting. 鈥淲e were involved from day one,鈥 explains Dave Younger, project engineer at building services subcontractor Aqua. 鈥淚t was very important that we understood what the client wanted and how the building was going to be used so we could make design suggestions.鈥
As a result, Aqua immediately proposed altering the way the water in the showers was heated, so that the system could cope with teams of squaddies bundling into the changing areas following training sessions.
Peter Whitmore, project manager of prime contractor Laing, says the specialists鈥 discussions with the client made a huge difference. 鈥淥nce the client has explained his needs to the whole team, this makes them feel more accountable,鈥 he says.
Laing organised the specialists into five clusters to reflect the project鈥檚 core areas. At Wattisham, these were the swimming pool, the frame and envelope, the substructure and external works, the finishes and the M&E work. Each cluster worked to find ways of cutting material and construction costs without compromising the functional design.
The groups also had a cluster leader who represented it at project design and site meetings, and took responsibility for detailing the design and improving construction processes within the group. Barnes, who led the substructure cluster, says: 鈥淲e made a lot of changes from concept design to construction.鈥
The foundations were designed initially as a reinforced concrete ground beam, but, following the team鈥檚 input, they were changed to strip foundations. 鈥淭his brought huge time savings,鈥 he says. Another change his cluster proposed was that the floor slab should be fibre-mix concrete laid in one operation rather than steel-reinforced concrete laid in bays. This was only possible because the team was in place to carry out the elaborate preplanning. 鈥淭he initial programme was for 18 weeks, but doing it this way we shaved off six,鈥 says Barnes proudly.
Communication between the clusters was essential if all specialists were to have an input into the project. The groups had weekly meetings, and regular value-engineering sessions with the client. On top of this, Laing insisted that the site foremen meet every morning to discuss what they were doing that day. These meetings ensured that the detailed construction planning could be made to pay off, and that operatives could get on with their work uninterrupted. 鈥淛ust by mentioning it in a meeting, the problem seems to go away,鈥 says Barnes. In this new spirit of teamworking, one phrase Barnes says he has not heard on this job is: 鈥淵ou priced for it; you build it.鈥
Aqua鈥檚 Younger concurs. 鈥淏y talking to each other, there was less wastage, and non-productive time was kept to a minimum. This means we get a productivity bonus, which is a great incentive.鈥
This arrangement earned many of the specialists a share in the savings generated, but communication was not just confined to individual clusters. 鈥淭he services contractor does not normally have any contact with the civils team,鈥 says Younger. At Wattisham, the civil engineer is installing heavy bases to the illuminated car park bollards ready for the electrical connection after the problem was raised at a team meeting.
However, there was a downside to the frequent meetings. 鈥淭he problem with spending so much time in meetings is the cost in overheads,鈥 says Younger. But, as Whitmore explains, cost-cutting was not allowed to affect the specification: 鈥淚f I鈥檓 being brutally honest, on a normal contract, most specialists would downspec to improve their margins.鈥 This did not happen at Wattisham. Levels of overhead and profit were agreed in advance and ringfenced; this meant that specialists鈥 recommendations were based on performance and not profit. The enhanced specification has resulted in a slight increase in capital expenditure, estimated to be in the region of 4%. However, as Whitmore is quick to point out, the project is 10% under budget on whole-life costs.
For Barnes, the new way of working meant integrating his own supply chain. 鈥淚 had to select subbies I could work with,鈥 he says. 鈥淚 felt I could not go out to competitive tender and end up with someone more used to working in knock-for-knock relationships.鈥
This egalitarian way of working did not suit all the design consultants. The fact that the views of the specialist contractors, the designers and the prime contractor were all given equal weight at the design meetings proved too much for some of Wattisham鈥檚 concept designers: architect Foster and Partners and structural engineer Waterman Partnership both left before the detailed phase had begun. And the newly influential specialists were actually involved in selecting their replacements. Whitmore says medium-sized design practices were targeted because they were felt to be more adaptable.
For the specialists, this close relationship with the consultants brought a new and unexpected benefit. It meant that consultants were aware of the pressure on contractors. 鈥淎 designer was never going to let you down; usually they responded to queries within hours鈥 says Barnes.
The next three prime contracts have already been announced 鈥 although the winners will not be named until March 鈥 and the MOD will be looking to implement the lessons learned on the two pilot projects. For Barnes, the lesson is simple: 鈥淚t was one team working towards one goal.鈥