Case study: Which bits qualify |
¾«¶«Ó°ÊÓ specification and capital allowances overview |
BCIS Ref | Element | Element description | Plant and machinery allowances claimed |
1 | Substructure | Pad foundations and ground beams | |
2 | Superstructure | | Ìý |
2a | Frame | Steel frame | |
2b | Upper floors | Reinforced concrete; 450 mm deep | |
2c | Roof | Lightweight reinforced concrete slab and asphalt | |
2d | Stairs | Precast concrete stairs and powder coated metal balustrades | |
2e | External walls | Curtain walling and rainscreen cladding and part planar glazing | |
2f | Windows and external doors | Double-glazed units within curtain-walling. Powder coated aluminium doors | Qualifying ironmongery |
2g | Internal walls and partitions | Fixed plasterboard partitions | |
2h | Internal doors | Hardwood veneered doors | Qualifying ironmongery |
3 | Internal finishes | | Ìý |
3a | Wall finishes | Three coats of emulsion to plasterboard walls. Ceramic tiling in toilets | |
3b | Floor finishes | Limestone floor to entrance, carpet and 600 × 600 mm raised access floors, | Carpets and matwells to cores |
| | Altro safety flooring to back-of-house areas | Ìý |
3c | Ceiling | Suspended concealed grid, metal panel tiling and plasterboard (acting as return extract air plenum) | Proportion of ceiling forming plenum ceiling |
4 | Fittings | Reception desk, signage, kitchen fittings and tea stations, sanitary appliances, vanity units | Qualifying fittings |
5 | Services | | Ìý |
5a | Sanitary appliances | Armitage Shanks sanitary ware | All sanitary appliances |
5c | Disposal installations | Cast-iron rainwater and foul water drainage and PVCu connections | Qualifying components |
5d | Water installations | Domestic-type hot and cold water services | Hot water services, and trace heating |
5e | Heat source | Gas-fired cast-iron sectional boilers with condensing heat exchanger | Boilers |
5f | Space heating and air treatment | 4-pipe fancoil air-conditioning installation | Air-conditioning installation |
5g | Ventilation systems | Toilet and kitchen extract ventilation | Toilet and kitchen extract ventilation |
5h | Electrical installations | LV distribution, LV power, power wiring to mechanical plant, lighting 500 × 500mm modular light fittings, basic lighting control installation, maintained emergency lighting, CCTV, cable containment | LV distribution, lighting controls, emergency lighting, power wiring to mechanical plant, CCTV |
5i | Gas installations | Gas distribution pipework to boilers | Gas distribution pipework |
5j | Lift and conveyor installations | Four eight-person lifts (one part goods) | Lifts |
5k | Protective installations | Dry risers, fire alarms, lightning protection | Dry risers, fire alarms |
5l | Communications installations | Cable containment for future telecommunications system | Cable containment |
5m | Special installations | ¾«¶«Ó°ÊÓ management system | ¾«¶«Ó°ÊÓ management system |
5n | Builders work in connection | Holes, chases, plinths and ducts for services | Builders work associated with qualifying expenditure barriers, street furniture, service ducts |
6 | External works and landscaping | Soft landscaping. External illuminated car park with automatic access barrier | Qualifying external works, car park |
7 | Preliminaries | Apportioned across the elements | Apportioned between qualifying and non-qualifying expenditure |
8 | Professional fees | Architect, structural engineer, services engineer, quantity surveyor, planning supervisor etc | Apportioned between qualifying and non-qualifying expenditure |