Public areas refurbishment |
| Element cost | cost/m2 gta £ | % of total cost |
Alterations and demolitions | 1,682,500 | 186.94 | 21.31 |
Strip out redundant M&E services, fittings and fixtures 9000 m2 @ 20 | Ìý | Ìý | Ìý |
Remove existing wall finishes 12,000 m2 @ 10 | Ìý | Ìý | Ìý |
Remove existing floor finishes including breaking up of screed 9000 m2 @ 38 | Ìý | Ìý | Ìý |
Extra for allowance for minor making good to existing floor slabs 2500 m2 @ 5 | Ìý | Ìý | Ìý |
Remove existing ceiling finishes 9000 m2 @ 12 | Ìý | Ìý | Ìý |
Demolish existing staircases and canopies Item @ 100,000 | Ìý | Ìý | Ìý |
Miscellaneous works to exterior; soft strip to facades; minor alterations to metal railings Item @ 20,000 | Ìý | Ìý | Ìý |
Demolish existing partitions 6000 m2 @ 20 | Ìý | Ìý | Ìý |
Demolitions and infill works to staircases and upper floors, including relocation of two staircases Item @ 275,000 | Ìý | Ìý | Ìý |
Demolitions and alterations to form new entrances Item @ 50,000 | Ìý | Ìý | Ìý |
Allowance for renovating and upgrading existing doors (average rate) 100 @ 350 | Ìý | Ìý | Ìý |
Allowance for reconfiguration of the layout of back of house/support areas 3000 m2 @ 100 | Ìý | Ìý | Ìý |
Refurbish existing finishes and fittings to existing WCs Item @ 20,000 | Ìý | Ìý | Ìý |
Stairs | 42,500 | 4.72 | 0.54 |
New main staircase; 4 m rise Item @ 20,000 | Ìý | Ìý | Ìý |
Metal handrails; to new and reconfigured staircases 150 m @ 150 | Ìý | Ìý | Ìý |
External walls | 16,000 | 1.78 | 0.20 |
New stone facings; to entrance 60 m2 @ 150 | Ìý | Ìý | Ìý |
Replacement soffit; to existing entrance canopy 100 m2 @ 70 | Ìý | Ìý | Ìý |
Windows and external doors | 130,000 | 14.44 | 1.65 |
Refurbishment and redecorate existing windows; replacement ironmongery Item @ 30,000 | Ìý | Ìý | Ìý |
Allowance for additional glass canopies to entrance Item @ 50,000 | Ìý | Ìý | Ìý |
Revolving entrance door with pass doors Item @ 50,000 | Ìý | Ìý | Ìý |
Internal walls and partitions | 385,000 | 42.78 | 4.88 |
140 mm blockwork 500 m2 @ 40 | Ìý | Ìý | Ìý |
Plasterboard partitions 1500 m2 @ 60 | Ìý | Ìý | Ìý |
Etched glazed partitions to food and beverage areas | Ìý | Ìý | Ìý |
Internal walls and partitions 400 m2 @ 550 | Ìý | Ìý | Ìý |
Double height, frameless feature glazed partitions to entrance areas 50 m2 @ 1100 | Ìý | Ìý | Ìý |
Internal doors | 235,700 | 26.19 | 2.99 |
Glazed automatic sliding doors 6 @ 12,000 | Ìý | Ìý | Ìý |
Glazed manual doors with stainless steel ironmongery, double leaf 8 @ 3000 | Ìý | Ìý | Ìý |
Hardwood doors and frames; ironmongery; single and double doors, average rate per leaf 90 @ 930 | Ìý | Ìý | Ìý |
Metal doors; single and double doors; average rate per leaf 32 @ 1750 | Ìý | Ìý | Ìý |
Wall finishes | 286,300 | 31.81 | 3.63 |
Plaster; generally 500 m2 @ 12 | Ìý | Ìý | Ìý |
Emulsion paint to plaster or lined walls 11,000 m2 @ 7 | Ìý | Ìý | Ìý |
Dry lining to walls and columns 2500 m2 @ 30 | Ìý | Ìý | Ìý |
Ceramic wall tiling to WCs, 100 × 100 tiles 250 m2 @ 85 | Ìý | Ìý | Ìý |
Hygienic board finish to walls and columns in the kitchen 700 m2 @ 50 | Ìý | Ìý | Ìý |
Decorative feature columns, integral lighting 6 @ 12,000 | Ìý | Ìý | Ìý |
Floor finishes | 800,100 | 88.90 | 10.14 |
Form ramp at entrance 90 m2 @ 120 | Ìý | Ìý | Ìý |
Raised floors 300 m2 @ 100 | Ìý | Ìý | Ìý |
Stone flooring and skirtings including screed to public areas, average rate 2450 m2 @ 185 | Ìý | Ìý | Ìý |
Ceramic floor tiling and skirtings including screed 300 m2 @ 80 | Ìý | Ìý | Ìý |
Carpet tiles, underlay, screed to public areas 2800 m2 @ 60 | Ìý | Ìý | Ìý |
Carpet tiles, MDF skirtings, screed to back-of-house areas 130 m2 @ 45 | Ìý | Ìý | Ìý |
Vinyl safety floor; screed; to public areas 2000 m2 @ 42 | Ìý | Ìý | Ìý |
Floor paint; back of house areas 600 m2 @ 12 | Ìý | Ìý | Ìý |
Painted softwood skirtings 1000 m @ 10 | Ìý | Ìý | Ìý |
Hardwood skirtings; stained 50 m @ 20 | Ìý | Ìý | Ìý |
Paint to existing skirtings 1200 m @ 5 | Ìý | Ìý | Ìý |
Ceiling finishes | 328,900 | 36.54 | 4.17 |
Suspended ceiling, plasterboard on MF, including allowancefor shadow gaps/detailing, to public areas 5640 m2 @ 35 | Ìý | Ìý | Ìý |
Suspended ceilings, mineral fibre tiles, to public areas 300 m2 @ 30 | Ìý | Ìý | Ìý |
Suspended ceiling; metal panel on exposed grid; to selected back-of-house areas 1000 m2 @ 40 | Ìý | Ìý | Ìý |
Suspended ceiling to kitchens, hygienic finish 300 m2 @ 45 | Ìý | Ìý | Ìý |
Bulkheads Item @ 20,000 | Ìý | Ìý | Ìý |
Allowance for access hatches 70 @ 200 | Ìý | Ìý | Ìý |
Feature ceilings in front-of-house areas Item @ 35,000 | Ìý | Ìý | Ìý |
Furniture and fittings | 556,000 | 61.78 | 7.04 |
Decorative screens 50 m @ 600 | Ìý | Ìý | Ìý |
Reception desk and concierge desks, MDF construction, veneer finish Item @ 75,000 | Ìý | Ìý | Ìý |
Allowance for features and permanent artwork Item @ 150,000 | Ìý | Ìý | Ìý |
Allowance for additional external signage Item @ 10,000 | Ìý | Ìý | Ìý |
Stone-topped bar and back bar (2) Item @ 80,000 | Ìý | Ìý | Ìý |
Allowance for restaurant fixed furniture, banquette seating, waiter stations, serving counters etc Item @ 156,000 | Ìý | Ìý | Ìý |
WC cubicles, front-of-house areas only 12 @ 1500 | Ìý | Ìý | Ìý |
Stone-topped vanity units to WCs 6 @ 2000 | Ìý | Ìý | |
Allowance for fittings to cloakrooms, meeting rooms etc Item @ 25,000 | Ìý | | Ìý |
Sanitary fittings | 15,100 | 1.68 | 0.19 |
WCs, urinals, wash hand basins, cleaners' sinks; generally (average rate used) 46 @ 300 | Ìý | Ìý | Ìý |
Allowance for disabled WC Item @ 1250 | Ìý | Ìý | Ìý |
Services equipment | 300,000 | 33.33 | 3.80 |
Allowance for kitchen equipment; including modifications to existing, plus gas connection Item @ 300,000 | Ìý | Ìý | Ìý |
Disposal installations | 45,500 | 5.06 | 0.58 |
Allowance for disposal, soil and vent installation to local stacks Item @ 5500 | Ìý | Ìý | Ìý |
Allowance for drainage from kitchen, bar and back of house areas Item @ 40,000 | Ìý | Ìý | Ìý |
Water installations | 50,000 | 5.56 | 0.63 |
Adapting and extending existing hot and cold water installation (350 points) Item @ 50,000 | Ìý | Ìý | Ìý |
Heating and air treatment | 150,000 | 16.67 | 1.90 |
Adapting and extending the existing space heating and air | Ìý | Ìý | Ìý |
Electrical installations | 877,500 | 97.50 | 11.12 |
Lighting and emergency lighting installation; to selected treatment systems Item @ 150,000 | Ìý | Ìý | Ìý |
front of house areas 4000 m2 @ 120 | Ìý | Ìý | Ìý |
Extra for scene-setting lighting and control systems to entrance, lobby and reception areas 1400 m2 @ 30 | Ìý | Ìý | Ìý |
Replacement and adapted small power installation to selected front of house areas 2200 m2 @ 10 | Ìý | Ìý | Ìý |
Allowance for enhanced small power to specialist areas Item @ 20,000 | Ìý | Ìý | Ìý |
Replacement and adaption of existing lighting and emergency lighting installation to back-of-house areas 2800 m2 @ 40 | Ìý | Ìý | Ìý |
Allowance for enhanced lighting in kitchen areas 300 m2 @ 60 | Ìý | Ìý | Ìý |
Replacement and adaption of small power installation to back-of-house areas 2800 m2 @ 20 | Ìý | Ìý | Ìý |
Extra for enhanced LV switch, sub mains distribution cabling and distribution boards to selected back-of-house areas 1100 m2 @ 25 | Ìý | Ìý | Ìý |
Earthing and bonding; generally Item @ 20,000 | Ìý | Ìý | Ìý |
Allowance for central battery emergency power system Item @ 50,000 | Ìý | Ìý | Ìý |
Allowance for controls and patch panels to meeting room suite Item @ 30,000 | Ìý | Ìý | Ìý |
Gas Installations | 3,000 | 0.33 | 0.04 |
Allowance for extending the gas supply to the kitchen, capped off supply (connection included with the kitchen equipment) Item @ 3000 | Ìý | Ìý | Ìý |
Communications installation | 301,000 | 33.44 | 3.81 |
Allowance for new wireways and adaptation of existing for security and fire alarms in selected public areas 2000 m2 @ 40 | Ìý | Ìý | Ìý |
Allowance for new wireways and adaptation of existing for security and fire alarms in back-of-house areas Item @ 11,000 | Ìý | Ìý | Ìý |
Allowance for additional works to wireways Item @ 10,000 | Ìý | Ìý | Ìý |
Allowance for upgraded fire detection and alarm installation Item @ 100,000 | Ìý | Ìý | Ìý |
Allowance for voice and data cabling Item @ 100,000 | Ìý | Ìý | Ìý |
Builders’ work in connection | 180,000 | 20.00 | 2.28 |
Builders' work in connection with services 9000 m2 @ 20 | Ìý | Ìý | Ìý |
Preliminaries & contingencies | 1,508,000 | 167.56 | 19.10 |
Preliminaries @ 15% Item @ 958,000 | Ìý | Ìý | Ìý |
Contingency sum @ 7.5% Item @ 550,000 | Ìý | Ìý | Ìý |
Total construction cost | Ìý | Ìý | Ìý |
Public areas only | 7,893,100 | 877.01 | 100.00 |