Cost breakdown |
| element cost £ | £/³¾2 gifa | % of total cost |
Internal doors | 104 000 | 13.16 | 1.18 |
Flush doors; fire-rated; solid-core veneer-faced; hardwood frames; ironmongery; complete | 55 | @ | £650 |
Flush doors; non-fire-rated; solid-core veneer-faced; hardwood frames; ironmongery; complete | 115 | @ | £550 |
Allowance for services access panels | item | @ | £5,000 |
Wall finishes | 114 400 | 14.48 | 1.30 |
Independent wall lining; plasterboard lining to inner face of external walls; two coats emulsion paint | 2500 | m2 @ | £14 |
Drylining; plasterboard to internal masonry walls; two coats emulsion paint | 1500 | m2 @ | £9 |
Two coats emulsion paint; to plasterboard partitions | 4050 | m2 @ | £3 |
Ceramic tiles; sand cement backing to plasterboard | 460 | m2 @ | £40 |
Vinyl wall finish to plasterboard | 1100 | m2 @ | £8 |
Extra for enhanced quality applied finishes in rest areas | 260 | m2 @ | £12 |
Two coats emulsion paint/dust sealer to blockwork | 1300 | m2 @ | £3 |
Hygienic finishes to kitchen areas; laminate panels | 325 | m2 @ | £60 |
Floor finishes | 525 000 | 66.46 | 5.96 |
Natural stone flooring, including allowances for screeds and skirtings to reception area | 50 | m2 @ | £100 |
Allowance for mats and matwells | item | @ | £5,000 |
Raised access floor; 500 mm deep floor void; including allowances for cavity barriers | 6650 | m2 @ | £42 |
Extra for seals to form airtight plenum, for forming holes in floor tiles and for fixing free issue supply air diffusers | 6500 | m2 @ | £4 |
Heavy-duty carpet tiles; including allowance for cutting holes for floor diffusers and skirtings to raised floor tiles | 6500 | m2 @ | £27 |
Anti-static vinyl floor tiles; bonded to raised floor tiles; including allowances for cutting holes for floor diffusers and skirtings | 150 | m2 @ | £18 |
Vinyl floor tiles; including allowance for screed and skirtings; to WCs and kitchen areas | 400 | m2 @ | £27 |
Semi-sprung beech strip flooring; including allowance for skirtings; to aerobics/gym | 100 | m2 @ | £60 |
Concrete hardener to raised floor plenums and plant rooms | 7350 | m2 @ | £2 |
Ceiling Finishes | 96 800 | 12.25 | 1.10 |
Suspended ceilings; mineral fibre tiles; semi-concealed grid; to office and support areas | 3150 | m2 @ | £26 |
Extra for moisture-resistant mineral fibre tiles to WCs | 250 | m2 @ | £5 |
Extra for acoustic tiles to aerobics areas/gym | 100 | m2 @ | £5 |
Suspended ceilings, hygienic metal tiles to kitchen areas | 250 | m2 @ | £40 |
Extra for enhanced ceiling finishes to reception, dining and rest areas | 315 | m2 @ | £10 |
Furniture and fittings | 255 600 | 32.35 | 2.90 |
Reception desk and fittings | item | @ | £10 000 |
Allowance for furniture and fittings to dining areas | item | @ | £50 000 |
Allowance for fixed equipment to gym/aerobics areas | item | @ | £10 000 |
Allowance for fittings; lockers, coat racks, shelves and so on | item | @ | £70 000 |
Statutory and directional signage | item | @ | £10 000 |
Allowance for decorative features, banners, graphics and so on to call centre areas | item | @ | £100 000 |
Window blinds | 140 | m2 @ | £40 |
Sanitary fittings | 33 900 | 4.29 | 0.38 |
WCs, urinals, wash-hand basins; generally | 105 | @ | £250 |
Allowance for fittings for disabled WCs | item | @ | £1,000 |
Showers; cabinets; trays; fittings | 6 | @ | £1,000 |
Cleaners’ sinks | 3 | @ | £200 |
Services equipment | 300 000 | 37.97 | 3.40 |
Catering installation complete; kitchen equipment; dishwash installation; servery fit-out | item | @ | £300 000 |
Disposal installations | 59 300 | 7.51 | 0.67 |
Rainwater disposal; cast iron downpipes and fittings | 7900 | m2 @ | £3.50 |
Waste, soil and vent installation; PVCu pipework and fittings | 7900 | m2 @ | £4 |
Water installations | 45 000 | 5.70 | 0.51 |
Hot and cold-water service; calorifiers; hot and cold-water storage; distribution | 150 | @ | £300 |