As the government attempts to ramp up housing construction, the new system of gateway checks on high rise buildings is adding anything up to 18 months to construction programmes. Joey Gardiner speaks to the regulator and industry experts to find out why
Last month student housing giant Unite broke cover about what is now one of the biggest issues facing developers of high-rise residential buildings in England. In a trading update, the firm revealed that delays caused by the 鈥渘ew approval gateways鈥 policed by the new building safety regulator (BSR) were forcing it to add 鈥渁round six months鈥 to project timelines.
Unite is by no means alone. David O鈥橪eary, executive director for policy at the Home Builders鈥 Federation, says some of the industry group鈥檚 members have reported waits of a year or more for approval. In the construction industry, of course, time is money, and there is mounting frustration across the sector over an issue that some say is having a profound impact on the development of high-rise resi schemes.
鈥淭his is huge,鈥 says O鈥橪eary. 鈥淚t鈥檚 right up there with the biggest issues the industry is facing.鈥
>> Also read: Reeves promises not to renege on building safety regulation as 90 new high-rise projects are held up by rules
>> Also read: The 精东影视 Safety Act is changing project procurement. Here鈥檚 how to navigate the way ahead
The delays relate to the new regime for high-rise residential buildings over 18 metres (HRBs) under the 2022 精东影视 Safety Act. The legislation stipulates that remediation or new-build HRB schemes must seek approval from the BSR at three separate 鈥済ateway鈥 points: planning approval; prior to construction; and prior to occupation.
The process is designed to provide security that the project has been fully designed prior to construction with its safety case properly thought through. However, the commencement of gateway 2 and gateway 3 checks is causing a significant hiatus as the regulator appears to be unable to deliver decisions within the promised timeframe.
Under the 精东影视 Safety Act, developers cannot get on site with construction until gateway 2 is passed. Industry experts say that delays at this crucial stage are making projects more costly and harder to get off the ground, just when the government is saying that it wants to turbo-charge housebuilding to deliver 1.5 million homes in five years.
So, how bad is the problem? And what are the chances it can improve?
Huge uncertainty
The 精东影视 Safety Regulator came into being in April 2023. The gateway 2 and 3 checks came into force from October that year, albeit under transitional arrangements, many 鈥渋n flight鈥 projects were in practice able to escape the requirement to submit schemes until 6 April, 2024. In advance of setting up, the regulations committed the BSR to turn around decisions at gateway 2 on remediation projects within eight weeks, and new-build schemes within 12 weeks.
However, the regulator began on the back foot, with the person leading the set-up, Peter Baker, resigning in April 2023 within days of its launch. Then, last summer, the collapse of a large private approved inspector, AIS, unexpectedly landed an additional 50 in-flight projects on the team.
The picture of its performance from parliamentary questions and freedom of information requests (FOIs) is concerning. Last September, Rushanara Ali, a junior government minister, that, by the end of June, only 2% of the 668 applications submitted had been determined in the promised timeframe, with 40% of applications refused.
>> Also read: Peter Baker: Meet the man who must ensure no repeat of Grenfell
According to various industry-submitted questions under the Freedom of Information (FOI) Act showing the picture up to September, only around 145 out of just over 1,000 projects had by then managed to secure approval at gateway 2. The FOI data obtained by the Construction Products Association found that a third of all applications submitted to date were then 鈥渦nder review鈥 waiting for determination.
These numbers fit with the anecdotal picture. Chris Martin, a director at London-based consultant Martin Arnold, which is involved both in new-build and recladding schemes, says one scheme has been in for over 30 weeks at gateway 2 without an outcome. 鈥淒evelopers are also telling us they have had projects rejected with very little feedback, and then you have to go to the back of the queue,鈥 he says. 鈥淭here鈥檚 just no confidence about the outcome.鈥
Delays experienced so far have, for the most part, happened before companies have even got to the final test point, gateway 3, which must be passed prior to occupation. Gateway 3 happens at the moment of maximum financial strain on a project, when all the outlay has been made, potentially stretching out the point at which developers can start generating income to pay back their investors and lenders.
Damien Sharkey, MD at London-based resi developer Hub, says the development programme is also lengthened because the gateway 2 approval requires the full building design to be much further advanced pre-construction. This already adds 鈥渕onths鈥 to the programme before the application is in.
Once in, he says it is now taking between 25 and 40 weeks currently to get decisions back at gateway 2, according to his consultant teams. From then he is making the assumption 鈥 few in the market have done it so far 鈥 that it may take another two to four months to get an approval at gateway 3 prior to occupation.
鈥淵ou factor in all three of those things and that adds something like 12 to 18 months to the development programme,鈥 he says. 鈥淚t is huge uncertainty and really challenging.鈥
Andrew Moore, head of operations, planning and building control at the BSR, admits that the organisation is 鈥渃ertainly not there yet鈥 on meeting the timeframes to process applications. 鈥淲e haven鈥檛 met target times yet, the time that we鈥檙e taking to assess is coming down, but we鈥檙e not at the statutory SLAs [promised service level agreement timeframes] yet.鈥
For some firms this is an existential challenge given the additional finance costs involved
David O鈥橪eary, executive director for policy at the Home Builders鈥 Federation
As evidence that some progress is being made, Moore provided data on the 186 decisions taken by the BSR since October last year, of which 57 (31%) were rejected. He said approvals were taken in an average of 22 weeks, with rejections happening significantly faster (17 weeks).
He also refutes the idea that applications have been rejected without feedback, saying all applicants are given both a face-to-face meeting and a follow-up very detailed point-by-point letter explaining the reasons why applications have failed. 鈥淚 really push back on the idea we鈥檙e not providing that detail. We鈥檙e being really clear,鈥 Moores says.
Existential challenge
Nevertheless, the delays for new-build work are being exacerbated by the fact that the regulator 鈥 for understandable reasons 鈥 has been prioritising remediation projects above new-build work.
The HBF鈥檚 O鈥橪eary says the issue is making developers think twice about bringing projects forward. 鈥淚t鈥檚 having a huge impact on anyone that works in the high-rise space,鈥 he says. 鈥淔or some firms this is an existential challenge given the additional finance costs involved. The real problem is just the unknowns.鈥
Martin, of Martin Arnold, says the issue is affecting whether schemes were viable, and forcing promoters to make some schemes taller in a bid to recoup additional costs incurred from the lengthening build programmes.
Hub鈥檚 Sharkey agrees. 鈥淲e鈥檙e having to factor in huge contingencies with our investors鈥 money, and this is affecting viability. Now we鈥檙e having to underwrite delay and the risk it might get refused,鈥 he says. 鈥淎nd gateway 3 is a huge financial strain when viability is already really challenged.鈥
The issue is also affecting contractor procurement, according to Natalie Taylor, senior associate at law firm Blake Morgan. Rather than go straight into a design and build contract, she says many developers are choosing to bring in contractors under flexible pre-construction services contracts until gateway 2 has been passed, because of fears about being hit with extension of time claims.
Taylor says most developers are at that point choosing to secure design and build contractors 鈥 despite continuing uncertainty over who bears the risk of further delays at the gateway 3 stage.
鈥淲hen do you sign a building contract, and who takes the cost risk? It鈥檚 just not clear,鈥 says Sharkey, who is gloomy about the wider implications of all this for housebuilding. 鈥淲e need to urgently reform this or things are going to grind to a halt, and we鈥檒l have no chance of meeting housing targets.鈥
Delivery model
So, what is causing the problem? Moore admits there were teething problems setting up the BSR. 鈥淲e鈥檙e new, so we鈥檝e been getting our processes and procedures sorted,鈥 he says. 鈥淎t the beginning that was the main cause of delays 鈥 it was us getting to grips with being a new regulator.鈥
Graham Watts, chief executive of the Construction Industry Council, says he has been attending a weekly Monday morning meeting for the past six months convened by Philip White, director of the BSR, designed to track and tackle the issues, with senior industry figures in attendance. While he defends many of the actions of the BSR, he admits: 鈥淚t鈥檚 true the regulator has taken an awful long time to set up and has struggled to recruit people. It has been short-staffed and under-resourced.鈥
Moore says the BSR is 鈥渋ncreasing our resources鈥 and that the time taken to assess applications is coming down, but he was unable to say when the regulator would be able to bring waits down to the expected timeframe. 鈥淚t feels like the BSR is not coping with the current level of applications, says the HBF鈥檚 O鈥橪eary. 鈥淭hey have increased resources recently, but it鈥檚 hard to recruit new and suitably qualified people with the expertise to do this work.鈥
Moore admits that the issues are wider than just new agency growing pains. He says the delivery model it has relied upon, where is has not used directly employed technical staff but instead pulled together multi-disciplinary teams 鈥 he calls them MDTs 鈥 from across local authority building control and the private sector to process each application, has not worked as well as expected.
Given the demand for skilled fire engineers, structural engineers and registered building inspectors in the market, Moore says it is taking on average over a month just to assemble a team to process an application, with each team individually sourced. 鈥淭he biggest cause by far at the moment of delays is getting the supply of support we need for our MDTs,鈥 he says, as the BSR has none of this technical expertise in-house.
鈥淲e have to go to the marketplace for every single project indiviually. Our SLA [timeframe] is almost finished by the time we get our support in place.鈥
And, while he says the work local authority building control staff have done has been invaluable, he admits the problem has been exacerbated by over-optimistic assumptions of how much support it could get from this source. He says the BSR is talking to the government about the fact the 鈥淢DT鈥 approach 鈥渋sn鈥檛 working as we鈥檇 hoped, and the best way to do this would be to have some dedicated resource within the BSR, so we can cut out delay鈥.
The question, he says, now is: 鈥淚f we can鈥檛 use MDTs better, what鈥檚 our plan B?鈥
No engagement
But beyond the problem of limited resources, developers also claim the way the regulator has been working has exacerbated delays. The BSR has said it will not engage in pre-application discussions with developers prior to submission.
Last summer it said in a statement that, despite the challenges and issues that the 鈥渄elays鈥 were causing, it would not assist applicants by 鈥渢ell[ing] you how to comply with the requirements of the building regulations鈥 or 鈥減rovid[ing] pre-application advice on building control applications鈥.
Applicants complain that this lack of engagement has left many in the dark as to what information will be required to get through the gateway checks, with applications then more likely to get rejected. Hub鈥檚 Sharkey says one result is that his various consultant teams are giving him different advice.
鈥淪ome are saying we need to be at [RIBA design] stage four, some are saying stage five. No one really seems to know what the deliverables are for the 精东影视 Safety Act. We鈥檙e going in a little blind,鈥 he says.
鈥淚f we could meet with them and get that certainty, then they won鈥檛 get frustrated about what鈥檚 being submitted.鈥
Stephen Beechey, group public sector director at contractor Wates, agrees that there has been 鈥渁 lack of engagement 鈥 it [the regulator] should be a service鈥.
Culture change
Others, including the regulator itself, take a very different view. The CIC鈥檚 Watts argues that the BSR has put 鈥渟o much guidance鈥 in the public domain, leaving applicant teams with no excuse for not knowing what to do.
鈥淭he accusation of a lack of engagement is just completely unfair,鈥 he says. 鈥淎nd it just emphasises the lack of preparedness of the sector. People just need to go and look for the guidance.鈥
Watts says one of the major factors behind the delays was simply that, aside from a tier of the very largest contractors, 鈥渢he industry wasn鈥檛 ready鈥. 鈥淲e saw many ridiculous examples of applications, people just asserting they鈥檇 met regulations. The regulator had to kick back an awful lot of applications,鈥 he says.
>>See also: Cost model: Evaluating the construction cost impact of the 精东影视 Safety Act
The BSR鈥檚 Moore agrees that a contributory factor behind the delays has been the sheer number of 鈥減roblematic鈥 applications which have had to be refused. 鈥淚 know the industry has done a lot of work,鈥 he says, 鈥渂ut, being totally candid, the penny hasn鈥檛 really dropped yet around what the BSR is looking for.
鈥淲hat we commonly get is, 鈥榊es we comply with part B, and here鈥檚 20,000 documents that show that鈥. What we need [in the application], and what we鈥檙e not getting, is an interpretation, something that explains how they鈥檝e worked it out. We鈥檙e not getting that narrative.鈥
Jon Pagan, head of technical at consultant Kiwa and chair of the Fire Engineering Council, says fault can be seen on both sides, with design teams really needing to 鈥渦p their game鈥. He said in a blog late last year that the refusal of the BSR to engage had led many people to 鈥渉ave a go鈥 at submitting applications on immature designs.
鈥淚s that the fault of the design teams for not understanding BSR鈥檚 requirements, or BSR鈥檚 fault for not explaining their requirements?鈥 he asks. 鈥淥ne way or another, this is not good.鈥
This to and fro over engagement stems from Dame Judith Hackitt鈥檚 call in her post-Grenfell review of industry regulation for the industry鈥檚 own consultants and experts to take full responsibility for their building designs, and stop leaning on the crutch of being told how to design by regulators. Moore confirms that this is exactly what has driven the BSR鈥檚 decision not to offer pre-application services to applicants.
鈥淭he reason we exist is because the old regime was marking its own homework,鈥 he says. 鈥淚t was telling people what to do and then marking that 鈥 don鈥檛 rely on us as a design expert.鈥
The CIC鈥檚 Watts says that, while the regulator鈥檚 attitude should not be a surprise, 鈥渦nfortunately, the vast majority of the industry has just been sitting back and saying they don鈥檛 have to do it, they don鈥檛 have to change.鈥
Kiwa鈥檚 Pagan says that, while Hackitt had rightly shown how designers were abusing the building control process, nevertheless the BSR鈥檚 process to address this has gone so far that there is now 鈥渘o contact on technical issues before the full gateway 2 submission鈥. He adds: 鈥淭his will make it very difficult to resolve any complex issues, and HRBs often have several of those.鈥
More change
While the latest data from the BSR suggests it is making some progress, there is now the potential for more upheaval to upset the applecart. The Grenfell Inquiry鈥檚 phase two report published in September last year contained a number of recommendations with significant ramifications for the regulation of the construction industry, to which prime minister Keir Starmer has promised to respond by 4 March.
Among these, is the recommendation for a single 鈥渟uper-regulator鈥 covering all health and safety issues related to construction, and which would include the newly formed BSR.
鈥淲e鈥檝e had enough teething problems just getting the building safety regulator off the ground working on 18-metre buildings. Once you expand that envelope considerably, can you just imagine what the problems are going to be?
Graham Watts, chief executive, Construction Industry Council
With Starmer expected to take the Grenfell Inquiry recommendations seriously, Watts says attempts to improve performance at the BSR are now starting to be hampered by resultant uncertainty about its long-term future, amid speculation about this 鈥渉uge super regulator鈥.
鈥淲e鈥檝e had enough teething problems just getting the building safety regulator off the ground working on 18 metre buildings. Once you expand that envelope considerably, can you just imagine what the problems are going to be?
鈥淵ou could have serious interruptions for the economic progress of the industry, which will obviously feed into the economy as a whole. If I was the regulator, I woul be wondering what鈥檚 going to happen.鈥
For the industry, then, it looks like any prospect of an imminent let up in the problems facing the high-rise sector are slim.
No comments yet